Timetable for Constructing Portions of the Lawrence Hopewell Trail


Phase 1

Completed through January 1, 2008

  • BMS/Hopewell campus
  • ETS corporate campus
  • Keefe Road
  • Village Park in Lawrenceville
  • Lawrenceville Main Street historic area
  • The Lawrenceville School campus

The most recent segment to open is Keefe Road, which with the other three segments in Lawrenceville provide a contiguous 3 mile stretch of trail. The BMS/Hopewell campus leg is approximately 1 mile along Pennington-Rocky Hill road. The segment through ETS property is approximately 1.2 miles on quiet paths off Rosedale Road.

Phase 2

Build segments between January 1, 2008 and December 31, 2008

  • Stony Brook-Millstone Watershed
  • Mercer County Park Northwest, including Rosedale Park
  • Tracts along Princeton Pike in Lawrence Township

Phase 3

Build segments between January1, 2009 and December 31, 2012

  • Complete the remaining sections of the entire 20-mile trail