Timetable for Constructing Portions of the Lawrence Hopewell
Trail
Phase 1
Completed through January 1, 2008
- BMS/Hopewell campus
- ETS corporate campus
- Keefe Road
- Village Park in Lawrenceville
- Lawrenceville Main Street historic area
- The Lawrenceville School campus
The most recent segment to open is Keefe Road, which with the other three segments in Lawrenceville provide a contiguous 3 mile stretch of trail. The BMS/Hopewell campus leg is approximately 1 mile along Pennington-Rocky Hill road. The segment through ETS property is approximately 1.2 miles on quiet paths off Rosedale Road.
Phase 2
Build segments between January 1, 2008 and December 31, 2008
- Stony Brook-Millstone Watershed
- Mercer County Park Northwest, including Rosedale Park
- Tracts along Princeton Pike in Lawrence Township
Phase 3
Build segments between January1, 2009 and December 31, 2012
- Complete the remaining sections of the entire 20-mile trail
|